Los Reyes Gold-Silver Project

Torex Gold Resources Inc. — Cosalá, Sinaloa & Durango, Mexico · Gold-Silver (doré) · NI 43-101 PEA · delivered September 2026
Report after-tax NPV(5%)US$1,491M
Independently rebuilt after-tax NPV(5%)US$1,239M
Variance vs report−16.9% (deliberate, decomposed)

What the rebuild surfaced. The study's after-tax NPV cannot be reproduced from its own tax disclosure: it applies a 30% rate stated to include the 8.5% special mining duty, which is not a construction Mexican law provides, and roughly US$265M of deductions are never named. Building the tax from the statutes leaves the rebuild 16.9% below the headline, decomposed line by line; in the study's own taxation reading the model ties to −0.06%, so the divergence is the tax build and nothing else.

Rebuilt economic modelExcel · formula-driven · every input footnoted · sensitivity dashboard · subscriber download
Investor memo10 pages · PDF · subscriber download

Downloads are delivered through the subscriber portal at launch. Two complete free sample sets are available in the library.

The first issue is free to everyone on the launch list

Join the list and you will receive the first full publication — the rebuilt Excel model and the ten-page investor memo — by email, free, when it releases. Founding subscriptions open afterwards for continued access to new analyses and the library. Founding subscriptions from US$99/month (launch pricing to be confirmed).